10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The CPC exam has 175 questions and runs 4 hours.

These 10 free CPC questions are organized by exam domain, so you can see how each part of the Certified Professional Constructor blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Project Scope Development 11% of exam

Question 1

Three qualified roofing subcontractors can meet the project schedule. Their bids differ only as follows: Hale bids $486,000 but excludes required perimeter flashing; Easton bids $512,000 for the complete scope; Park bids $501,000 but excludes required testing. Firm, scope-complete quotes to cover the exclusions are $18,000 for flashing and $14,000 for testing. Each bid already includes a $10,000 material allowance that must remain in the scope. The constructor is comparing total costs, including any separately purchased work. Which bid has the lowest evaluated total?

Show answer & explanation

Correct answer: C - Hale, evaluated at $504,000.

Domain 2: Employment Practices 9% of exam

Question 2

A private contractor's FLSA-covered, nonexempt carpenter works beyond 40 hours in the established workweek after the superintendent asks the crew to finish a pour. The time is accurately recorded. The project manager refuses to approve it because company policy requires advance written authorization for overtime. Which payroll instruction complies with the Fair Labor Standards Act?

Show answer & explanation

Correct answer: C - Pay the recorded time, including required overtime; address authorization separately.

Domain 3: Working Relationships 12% of exam

Question 3

Three successive floor handoffs show the same pattern: framing is accepted Monday; the inspector signs the wall-closure release Tuesday morning; the full planned drywall crew and all required materials are ready for Wednesday's planned start; and the drywall foreman receives the closure authorization Friday afternoon. Inspection releases reach the foreman through the project engineer's weekly report. Which failure best explains the late drywall starts?

Show answer & explanation

Correct answer: B - Delayed transmission of completed inspection releases to the drywall foreman.

Domain 4: Construction Start-up and Support 10% of exam

Question 4

Today's inspection-and-test plan identifies two controls: Hydrostatic testing: a witness point. After two working days' acknowledged notice, testing may proceed if the owner's witness does not attend. Pipe insulation: a hold point requiring the engineer's written release after review of the test results. The notice requirement has been met, the test setup is ready, and the owner's witness is absent. No insulation release has been issued. Which instruction should the superintendent give?

Show answer & explanation

Correct answer: D - Perform the pressure test; hold insulation until the engineer issues the written release.

Domain 5: Construction Resource Management 12% of exam

Question 5

A loader fills one truck with 12 loose cubic yards in 6 minutes. Hauling, dumping, and returning take another 24 minutes per truck. The loader serves one truck at a time, all trucks are identical, and there are no other delays or production constraints. For steady operation, which fleet is the smallest that keeps the loader continuously supplied, and what production can that fleet sustain?

Show answer & explanation

Correct answer: A - Five trucks; 120 loose cubic yards per hour.

Domain 6: Construction Cost Control 12% of exam

Question 6

Month-end cost report for a concrete work package: Budget at completion: $1,200,000 Earned value: $480,000 Actual cost: $600,000 The entire cost overrun to date arose from a completed, one-time repair. A review confirms that the remaining unchanged scope can be completed at its original budgeted cost, with no recurrence of the repair. What estimate at completion is consistent with that assessment?

Show answer & explanation

Correct answer: B - $1,320,000

Question 7

The owner's authorized representative issues a written directive to reroute a utility. The contract requires the constructor to proceed with directed changes, give written notice of any requested adjustment within five calendar days, and submit pricing later. The directive does not settle price or time. Work can proceed safely, but the subcontractor needs ten calendar days to prepare its quotation. Which response protects the constructor's contractual position?

Show answer & explanation

Correct answer: C - Proceed, give timely notice, and track the changed work's costs and schedule effects.

Domain 7: Project Closeout 10% of exam

Question 8

An air-handling unit starts, its measured airflow meets design, and its manual controls operate. During functional testing, however, the outdoor-air dampers remain open when the approved unoccupied sequence requires them to close. The contract requires successful sequence testing and operator training before system turnover. Which closeout status accurately describes the equipment?

Show answer & explanation

Correct answer: B - Start-up is complete; the required functional commissioning has not passed.

Domain 8: Construction Risk Management 11% of exam

Question 9

After an overnight storm, the competent person inspects a 9-foot-deep trench and finds new tension cracks, soil sloughing below a brace, and accumulating water. The installed shoring had been accepted for dry conditions. The crew is waiting outside the trench. What must occur before entry resumes?

Show answer & explanation

Correct answer: A - Keep entry suspended until changed conditions are reassessed and adequate cave-in and water-accumulation protection is implemented.

Domain 9: Ethics 13% of exam

Question 10

Before scoring proposals for a private project's curtain-wall package, the constructor learns that one bidder is owned by the constructor's sibling. The relationship has not been disclosed, and the constructor has not reviewed any prices. The owner's policy permits related firms to compete when the relationship is disclosed and an independent evaluator makes the award recommendation. How should the constructor handle the evaluation?

Show answer & explanation

Correct answer: D - Disclose the relationship and have an independent evaluator take over both scoring and the award recommendation.